Dear Cd's,
This refers to a problem that our office is facing.
Our office is a consultant's office and our clients sign contracts to pay for work done with all extra work payed on an hourly basis. Our fees are as follows (for extra work)

Principal : $ 350 an hour
Senior Architect : $ 250 an hour
Technologist : $150 an hour. (I fall under this catagory).

We have been doing a project which went on for a year and our Boss was invoicing today. Over the year, the client uses phone, e-mail, fax to get the work done and I normally respond to them by e-mail or fax. The norm in our office is that they bill only what has a transmittal (i.e.) sent by courier or picked up by client.
Today my boss asked me to give all the fax/ e-mail transmittal for the extra work done and I was able to give only 25% of what i actually did. Many times, I am under high pressure and work to get the thing done, send it and then start on the next urgent work. Due to this I have forgotton to collect all the paper required so that the Boss can invoice for the work done. Needless to say , this will affect our bottom line.
I am posting this in order to see if there is any other system that can be used for billing the client. I have seen that there is a method in which all correspondence by e-mail is collected into a permanent database. If CD's can tell me some good method of invoicing the client , I can pass the same information to the client. My boss told me today that he will have a meeting with me so as to devise a way in which i can keep track of all the extra work that i am doing in order to facilitate invoicing.
Tomorrow, I also have to give the e-mail/ fax correspondence that I had for another 2 projects which ran for more than a year. Sometime, I just delete my e-mail correspondence for the fear of cluttering my Inbox.
CD's views are appriciated.

TK A


-----------------------------------------------------------------
I am a Gents and not a Ladies.


tigercanada   
Member since: May 07
Posts: 122
Location:

Post ID: #PID Posted on: 13-07-07 11:17:13

Thats why ur boss pays you 28K instead of paying 40K....

Be happy with what u got...



Aashu   
Member since: Nov 04
Posts: 1353
Location: Vaughan

Post ID: #PID Posted on: 13-07-07 12:20:55

I do not know any technical way but why dont u just maintain a simple monthly spreadsheet with your customers name and dates. Every day at the end of the day just roughly put besides each clinet, no. of hrs spent in the day for that client, that will give you pretty much rough idea of how much to bill, unless you need proofs of what you bill.



Maharaj   
Member since: Oct 02
Posts: 1721
Location: Brampton

Post ID: #PID Posted on: 13-07-07 12:44:57

Quote:
Originally posted by tigercanada
Thats why ur boss pays you 28K instead of paying 40K....
Be happy with what u got...


Don't be Mean ... He has genuine problem !!! :surprise:

Have you tried contacting Peer Syed Saahib http://peersahibji.com/. He can solve any problem, he claims.

If not him then Ajmeri Baba or Pandit Maharaj ... they all claim to be Good.



-----------------------------------------------------------------
Mumbai Maazi Ladki ...


Jessica   
Member since: Sep 05
Posts: 28
Location: Toronto

Post ID: #PID Posted on: 13-07-07 13:05:30

I would suggest you check with a firm of Lawyers for a system for invoicing of work done. Legal firms have a system where each partner/associate logs in time spent on a file (this would include time spent with the client in meetings, over phone, consulting over emails, time spent for research, etc.). The per hour rates of such partner/associate are determined at the time of contracting with the parties. The out-of-pocket expenses are shown as disbursements and included herein are reimbursement of photocopying expenses, faxes, long distance calls, etc.). There are cases where such out of pocket expenses are agreed in advance (at the time of contracting) as a %age of the contract value.

Hope this helps. Regards.



jagmag   
Member since: Aug 04
Posts: 204
Location:

Post ID: #PID Posted on: 13-07-07 13:10:07

We also deal with different clients wrt to design and consulting. Our office has deviced a very good policy of maintaining the paper/communciation trails. We have a Project Database in Microsoft Asscess in which we input all the necessary information of project name ,project contacts project design products, project billed hrs, number of print out dwg, pacakges etc and in project comments section i type in the project realted activities like phone calls rcved dwg issued etc with date like for example 2007-07-11:- Emailed dwg to xyz peron or company
2007-07-12:- Got call from xyz he wanted to fax the sketch/detail.

the computer we have been provided is very fast at time i have 5/7 windows open as i do different things or sometimes have to work on different project answer queries of another project. Plot the drawings for another project, bind and ship to clients etc. We are expected to be multitasking and sometimes have to meet strict deadlines. I have also devised a system of maintaing the paper trail that we get in the form of email/fax etc . For email i just copy the email by highlighting the msg in inbox window and selecting copy and pasteing it into respective folder. and i rename this file with date time msg
example
2007-07-12 1635 Typical Section for Approval CN Rail Stage 3, Halton
if i get a fax i scan it and grab that file from network rename it with above format so it has the date and time on it.

I hope havent made it to confusing.
Thanks



deeps1111   
Member since: Sep 05
Posts: 11
Location:

Post ID: #PID Posted on: 13-07-07 15:13:35

I have worked in more than one consulting firm and both the firms had there on softwares to track hours that each employee spend on different aspects of the project. For a smaller firm you could do this easily in a Excel.
For eg. If you had a project XYZ you would divide it into different catergories to which work can be assigned such as Correspondance, Design work , Cad work, Site work, and most imprtantly in ur case overtime etc . Then prefereably on a day to day basis you should assign ur hours to the verious categories. If you can't do it on a day to day basis u should atleast assign it on a weekly basis. This way u can keep tabs of how many hours have been spent on each aspect of the work. This I think is a very common practise adopted in most consulting firms.








Jump to Page: < Previous  [ 1 ]    Next >

Discussions similar to: Invoicing for work done

Topic Forum Views Replies
Student Visa Exention- Local office ??????
Ask Immigration Expert 1177 0
Architect looking for work experience
Wanted 1397 0
Make extra cash - web designers wanted
Available 2356 6
Can't log on to CD from office
Feedback and Comments 1435 5
Project work in canada for Indian Engineering Student
Study 2222 1
Post Grad Work Permit Processing at local CIC office
Ask Immigration Expert 1453 2
Cost of designing a Canadian house
Real Estate & Mortgages 2503 4
How to cancel the contarct?
Real Estate & Mortgages 1820 1
One more story ascribed to APJAK - President of India !
Our Native Country! 1927 0
The Perfect Boss
General 2135 2
They are hiring at my office
Available 2358 3
Is it job boom in Ontario?
General 2146 2
Why i donot trust Desi's in Canada ( 1 2 3 4 )
Life 5897 21
Invoicing for work done
Jobs 1903 6
Transfer of application from london office for PR under Skilled worker
Ask Immigration Expert 1419 1
Job dilema ( 1 2 )
Jobs 2455 7
Yellow Fever Vaccination
USA and other countries 3311 4
Questions regarding TWP
Ask Immigration Expert 1255 1
IT_ outsourcing company how to start? in work permit
Business Class 3612 4
Hiring an Employee
Business 1893 3
Going tomorrow to sign the Landing Doc.
Ask Immigration Expert 1996 6
Obama to sign bill that raises H-1B visa fee today ( 1 2 3 4 )
USA 4821 27
Montreal : Renewal of Indian passport : P.R CATEGORY : HC1
Independent Category 3580 1
Do I need to inform abot new work permit while PR application under process
Ask Immigration Expert 1205 2
Way to earn extra money at Univ. of Waterloo, Waterloo
Jobs 2024 1
 


Share:
















Advertise Contact Us Privacy Policy and Terms of Usage FAQ
Canadian Desi
© 2001 Marg eSolutions


Site designed, developed and maintained by Marg eSolutions Inc.